    The Longest Path Through a Network Diagram That Determines the Earliest
Solved

The Longest Path Through a Network Diagram That Determines the Earliest

Question 34

Question 34

Multiple Choice

The longest path through a network diagram that determines the earliest completion of a project is called the ____ path.


A) essential
B) important
C) critical
D) vital

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q29: The _,an international professional society for project

Q30: A project should be developed using progressive

Q31: Project managers should possess general management knowledge

Q32: Project _ management is concerned with making

Q33: According to the Standish Group study describing

Q35: Project management tools and _ assist project

Q36: Projects rarely involve uncertainty.

Q37: _ tools are often recommended for small

Q38: The project _ usually provides the direction

Q39: The "CHAOS" study found that more than

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines