    In PERT,the Activity Duration Time Is Equal To
Solved

In PERT,the Activity Duration Time Is Equal To

Question 21

Question 21

Multiple Choice

In PERT,the activity duration time is equal to:


A) pessimistic time
B) optimistic time
C) most likely time
D) mean duration

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q14: To determine how to crash activity times<br>A)

Q19: The critical path for this network

Q22: Suppose that,after analyzing a PERT/CPM ntwork,the project

Q25: Three paths of a PERT network

Q39: Activities G,P,and R are the immediate predecessors

Q40: Which of the following is always true

Q49: Activities require time to complete while events

Q49: The length of time an activity can

Q51: Activities K,M,and S immediately follow activity H,and

Q56: Which of the following is a general

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines