Essay
A project consists of five activities.Naturally the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within 9 hr.?
Correct Answer:

Verified
a.
b.8 hr...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q13: When activity times are uncertain,an activity's most
Q19: PERT and CPM<br>A)are most valuable when a
Q22: Constraints in the LP models for crashing
Q27: PERT and CPM are applicable only when
Q28: Arcs in a project network indicate<br>A)completion times.<br>B)precedence
Q35: Slack equals<br>A)LF - EF.<br>B)EF - LF.<br>C)EF -
Q48: National Oil Company (NATOCO)must plan the
Q49: From this schedule of activities,draw the
Q54: A senior MIS design class project
Q56: Mary Yetter,a staff analyst at the