Solved

A Project Has the Following Activities,durations,costs,and Precedence Relationships Develop a Cost-Time Trade-Off Analysis

Question 43

Essay

A project has the following activities,durations,costs,and precedence relationships:  Present  Duration  (Weeks)  Accelerated  Duration  (Weeks)  Immediate  Predecessor  Activities  Present  Cost  Accelerated  Cost  A 109$11,000$15,000 B 151320,00025,000 C 106 A 9,00020,000 D 2018 A 25,00030,000 E 1510 C 20,00035,000 F 1715 B 20,00030,000 G 1210 B 15,00025,000 H 98 D,F 12,00018,000 I 76 G, H 10,00015,000\begin{array} { c c c c c c } \hline & \begin{array} { c } \text { Present } \\\text { Duration } \\\text { (Weeks) }\end{array} & \begin{array} { c } \text { Accelerated } \\\text { Duration } \\\text { (Weeks) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } \\\text { Activities }\end{array} & \begin{array} { c } \text { Present } \\\text { Cost }\end{array} & \begin{array} { c } \text { Accelerated } \\\text { Cost }\end{array} \\\hline \text { A } & 10 & 9 & \cdots & \$ 11,000 & \$ 15,000 \\\text { B } & 15 & 13 & \cdots & 20,000 & 25,000 \\\text { C } & 10 & 6 & \text { A } & 9,000 & 20,000 \\\text { D } & 20 & 18 & \text { A } & 25,000 & 30,000 \\\text { E } & 15 & 10 & \text { C } & 20,000 & 35,000 \\\text { F } & 17 & 15 & \text { B } & 20,000 & 30,000 \\\text { G } & 12 & 10 & \text { B } & 15,000 & 25,000 \\\text { H } & 9 & 8 & \text { D,F } & 12,000 & 18,000 \\\text { I } & 7 & 6 & \text { G, H } & 10,000 & 15,000 \\\hline \hline\end{array} Develop a cost-time trade-off analysis.Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost.Determine each step's cost and the duration of the project.

Correct Answer:

verifed

Verified

blured image blured image Project is reduced...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions