The Fixed Manufacturing Overhead Budget Variance Equals

Question 159

Multiple Choice

The fixed manufacturing overhead budget variance equals:


A) Actual fixed manufacturing overhead cost − Applied fixed manufacturing overhead cost.
B) Actual fixed manufacturing overhead cost − Budgeted fixed manufacturing overhead cost.
C) Budgeted fixed manufacturing overhead cost − Applied fixed manufacturing overhead cost.
D) Actual fixed manufacturing overhead cost − (Actual hours × Standard fixed manufacturing overhead rate) .