(Appendix 7A) Lemaire Corporation Is Conducting a Time-Driven Activity-Based Costing

Question 97

Multiple Choice

(Appendix 7A) Lemaire Corporation is conducting a time-driven activity-based costing study in its Customer Support Department. The company has provided the following data to aid in that study:
(Appendix 7A)  Lemaire Corporation is conducting a time-driven activity-based costing study in its Customer Support Department. The company has provided the following data to aid in that study:        -On the Capacity Analysis report in time-driven activity based costing,the  unused capacity in minutes  would be closest to: A)  806,620 minutes B)  723,380 minutes C)  765,000 minutes D)  744,190 minutes (Appendix 7A)  Lemaire Corporation is conducting a time-driven activity-based costing study in its Customer Support Department. The company has provided the following data to aid in that study:        -On the Capacity Analysis report in time-driven activity based costing,the  unused capacity in minutes  would be closest to: A)  806,620 minutes B)  723,380 minutes C)  765,000 minutes D)  744,190 minutes (Appendix 7A)  Lemaire Corporation is conducting a time-driven activity-based costing study in its Customer Support Department. The company has provided the following data to aid in that study:        -On the Capacity Analysis report in time-driven activity based costing,the  unused capacity in minutes  would be closest to: A)  806,620 minutes B)  723,380 minutes C)  765,000 minutes D)  744,190 minutes
-On the Capacity Analysis report in time-driven activity based costing,the "unused capacity in minutes" would be closest to:


A) 806,620 minutes
B) 723,380 minutes
C) 765,000 minutes
D) 744,190 minutes

Correct Answer:

verifed

Verified