Essay
Posson Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.The company based its predetermined overhead rate for the current year on 20,000 machine-hours,total fixed manufacturing overhead cost of $130,000,and a variable manufacturing overhead rate of $3.00 per machine-hour.Job K789,which was for 10 units of a custom product,was recently completed.The job cost sheet for the job contained the following data:
Required:
a.Calculate the predetermined overhead rate for the year.
b.Calculate the amount of overhead applied to Job K789.
c.Calculate the total job cost for Job K789.
d.Calculate the unit product cost for Job K789.
Correct Answer:

Verified
a.Estimated total manufacturing overhead...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q180: Branin Corporation uses a job-order costing system
Q181: Leeds Corporation uses a job-order costing system
Q182: Claybrooks Corporation has two manufacturing departments--Casting and
Q183: Kroeker Corporation has two production departments, Milling
Q186: Fusaro Corporation uses a predetermined overhead rate
Q187: Luarca Corporation has two manufacturing departments--Casting and
Q188: Nielsen Corporation has two manufacturing departments--Machining and
Q189: Lightner Corporation bases its predetermined overhead rate
Q190: Lupo Corporation uses a job-order costing system
Q254: An employee time ticket is an hour-by-hour