Multiple Choice
Taylor is writing a progress report on development of a new software program for a client.She and her team faced a technical glitch last week which however,has been solved now.Which of the following is the best way to present this information to the client?
A) "I'm really sorry, but we're running 2 days behind schedule. We will however be back on schedule by the end of the month."
B) "We have had a major problem last week because of which our work is affected to an extent. However, we should be able to finish by the due date."
C) "We overcame a major technical glitch last week. We are now on track and expect to finish the work by the due date."
D) "After correcting the huge problem we had last week, we should be back on track by due date if we face no other glitches."
E) "Please accept our sincere apologies. We will be unable to complete the work according to the estimated deadline."
Correct Answer:

Verified
Correct Answer:
Verified
Q46: Ethan Hill who works for Small Steps,a
Q47: How important is an executive summary in
Q48: Sales proposals,particularly for complicated systems costing millions
Q49: Progress reports consist of the work that
Q50: Which of the following questions does the
Q52: Which of the following should be undertaken
Q53: One should begin a proposal with a
Q54: Proposals must stress benefits for all affected
Q55: A proposal that goes outside an organization
Q56: A good progress report presents good news