The forward pass in a critical path algorithm involves:
A) Calculating the late finish and late start for each task.
B) Calculating the late finish and the earliest possible start times for each task.
C) Calculating the earliest possible start and finish times for each task.
D) Calculating the earliest possible start and late start for each task.
Correct Answer:

Verified