Multiple Choice
Fee The first step is to calculate the estimated total overhead costs in the two departments.
Machining
Customizing
The second step is to combine the estimated manufacturing overhead costs in the two departments ($44,400 + $21,200 = $65,600) to calculate the plantwide predetermined overhead rate as follow:
The overhead applied to Job C is calculated as follows:
Overhead applied to a particular job = Predetermined overhead rate x Machine-hours incurred by the job
= $6.56 per MH x (4,100 MHs + 1,600 MHs)
= $6.56 per MH x (5,700 MHs)
= $37,392
Job C's manufacturing cost:
Reference: CH02-Ref24
Prather Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data:
Recently, Job P513 was completed with the following characteristics:
-The total job cost for Job P513 is closest to:
A) $690
B) $900
C) $1,400
D) $1,210
Correct Answer:

Verified
Correct Answer:
Verified
Q197: Cull Corporation uses a job-order costing system
Q199: Gerstein Corporation uses a job-order costing system
Q200: Gerstein Corporation uses a job-order costing system
Q201: Bolander Corporation uses a job-order costing system
Q203: Morataya Corporation has two manufacturing departments--Machining and
Q204: Mcewan Corporation uses a job-order costing system
Q205: Dejarnette Corporation uses a job-order costing system
Q206: Mahon Corporation has two production departments,Casting and
Q307: A company will improve job cost accuracy
Q353: The amount of overhead applied to a