Multiple Choice
A time series is shown below.Perform single exponential smoothing for this data set using α = 0.2. What is the value of the forecast for period 6?
A) 40
B) 36
C) 31.5
D) 33.2
Correct Answer:

Verified
Correct Answer:
Verified