Short Answer
A large disaster cleaning company estimates that 30% of the jobs it bids on are finished within the bid time. Looking at a random sample of 8 jobs that is has contracted:
-Calculate the probability that exactly 4 of the jobs were not completed within the bid time.
Correct Answer:

Verified
.1361
P(x ...View Answer