Multiple Choice
Which desirable action that managers take to relieve bottleneck constraints of the assembly operation do managers note that the cost of poor quality at a nonbottleneck operation is the cost of materials wasted?
A) Eliminate idle time at the bottleneck operation.
B) Shift products that are not made on the bottleneck machine to nonbottleneck machines,or to outside processing facilities.
C) Reduce setup time and processing time at bottleneck operations.
D) Improve the quality of parts,or products,manufactured at the bottleneck operation.
E) Other operating costs will increase,while contribution margin will remain unchanged because bottleneck capacity of the assembly operation will not increase.
Correct Answer:

Verified
Correct Answer:
Verified
Q110: Which of the following is not an
Q111: Past costs are historical costs,and _.<br>A)constraints only<br>B)make-or-buy
Q112: The managers at the Wicker Basket Manufacturing
Q113: Sales-order costs are batch-level costs that are
Q114: To determine product mix,managers maximize operating income,subject
Q115: The book value of an old machine
Q116: All separable costs are incremental costs.
Q118: In which step of the decision-making process
Q119: The manager at the Engine Testing Organization
Q120: Which of the following is not true