Which of the Following Is Not a Desirable Management Action

Question 26

Multiple Choice

Which of the following is not a desirable management action to relieve the bottleneck constraint of the assembly operation?


A) Eliminate idle time at the bottleneck operation.
B) Shift products that do not have to be made on the bottleneck machine to nonbottleneck machines,or to outside processing facilities.
C) Reduce setup time and processing time at bottleneck operations.
D) Improve the quality of parts,or products manufactured,at the bottleneck operation.
E) Emphasize that poor quality is less costly at a bottleneck operation compared to the nonbottleneck operation.