Multiple Choice
In the case of a fixed price contract,AASB 111 specifies four conditions that must all be met in order for the percentage-of-completion method to be applied.These conditions include:
A) Costs related to the contract can be clearly identified and measured reliably.
B) It is probable that the economic benefits arising from the contract will flow to the contractor.
C) The entity commissioning the work has a good credit rating and is able to pay its debts.
D) Costs related to the contract can be clearly identified and measured reliably and it is probable that the economic benefits arising from the contract will flow to the contractor.
Correct Answer:

Verified
Correct Answer:
Verified
Q34: Revenues may be generated by:<br>A) holding and
Q35: Which of the following is not a
Q36: The following is a diagram of the
Q37: Gains never arise from the ordinary activities
Q38: Describe the output and input measures of
Q40: With the percentage-of-completion method of accounting for
Q41: The following journal entries were recorded by
Q42: Hillier Construction Ltd commenced the construction
Q43: Biological assets are:<br>A) recognised as income when
Q44: When goods are sold on extended credit