Multiple Choice
The percentage of completion can be measured in a number of ways,including:
A) physical estimates or surveys of the work performed to date.
B) the work plan basis, which uses the project management plan to calculate the percentage of the construction completed.
C) the billings basis, using the proportion that progress billings to date bear to the total estimated billings for the contract.
D) physical estimates or surveys of the work performed to date and the billings basis, using the proportion that contract costs incurred for work performed to date bear to the estimated total contract costs.
Correct Answer:

Verified
Correct Answer:
Verified
Q60: When the outcome of a construction contract
Q61: IASB and FASB initiated a joint project
Q62: If the borrower prepays interest,the inflow of
Q63: The general rule under modified historical-cost accounting
Q64: Russell Ltd commenced the construction of
Q66: Bellarine Ltd is publisher of Mode magazine
Q67: Using the cost method to calculate the
Q68: Where the percentage-of-completion method is based on
Q69: Which of the following statements is not
Q70: In the situation that a debtor becomes