Multiple Choice
Zellars,Inc.is considering two mutually exclusive projects,A and B.Project A costs $95,000 and is expected to generate $65,000 in year one and $75,000 in year two.Project B costs $120,000 and is expected to generate $64,000 in year one,$67,000 in year two,$56,000 in year three,and $45,000 in year four.Zellars,Inc.'s required rate of return for these projects is 10%.The modified internal rate of return for Project A is
A) 19.19%.
B) 24.18%.
C) 26.89%.
D) 29.63%.
Correct Answer:

Verified
Correct Answer:
Verified
Q42: Positive NPV projects may be rejected when
Q44: What is the net present value's assumption
Q58: If a project is acceptable using the
Q63: Advantages of the payback period include that
Q92: Your firm is considering an investment that
Q102: For the net present value (NPV)criteria,a project
Q137: A project's net present value profile shows
Q138: Finance theory suggests that the IRR criterion
Q140: If a project is acceptable using the
Q141: The payback period may be more appropriate