Multiple Choice
Zellars,Inc.is considering two mutually exclusive projects,A and B.Project A costs $95,000 and is expected to generate $65,000 in year one and $75,000 in year two.Project B costs $120,000 and is expected to generate $64,000 in year one,$67,000 in year two,$56,000 in year three,and $45,000 in year four.Zellars,Inc.'s required rate of return for these projects is 10%.Which project would you recommend using the replacement chain method to evaluate the projects with different lives?
A) Project B because its NPV is higher than Project A's replacement chain NPV of $47,623.
B) Project A because its replacement chain NPV is $76,652, which exceeds the NPV for Project B.
C) Project A because its replacement chain NPV is $45,642, which is less than the NPV for Project B.
D) Both projects will be valued the same since they are now both four year projects.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Many financial managers believe the payback period
Q25: A significant advantage of the payback period
Q30: The internal rate of return will equal
Q32: Two projects that have the same cost
Q73: What is the internal rate of return's
Q100: Project A has an internal rate of
Q109: If two projects are mutually exclusive,then the
Q111: The most critical aspect in determining the
Q119: Calculating the modified internal rate of return
Q156: If a project is acceptable using the