Essay
You were just promoted to manage the process defined by the four stages A to D below. This process could be a human resource management, marketing, accounting, finance, or engineering process and you are the manager. This is your chance to impress your boss and be promoted again. After three months on the job you realize something is not right with the process because your employees experience big pile ups of work, things take too long to be processed, the opportunity for error is increasing, and the entire process is approaching chaos. Do a process and capacity analysis of this process. The numbers in parentheses (#) are the times in minutes to complete one unit of work. Demand on the process averages 30 units per hour and each unit must be worked on by all four stages. Administrative clerk(s) do Stage A work. The assistant manager(s) do Stages C and D work. The coding specialist(s) do Stage B work. Currently, there are 3 administrative clerks, 2 coding specialists, and 3 assistant managers on duty. Each assistant manager is cross-trained so he/she can do Stage C or Stage D work.
a.Which stage of work is the bottleneck? What is the capacity (in units per hour) at the bottleneck stage?
b.What should the throughput rate be set at so that the utilization at the bottleneck stage is 90%?
c.Based on your throughput rate found in question b above, what will be the utilization at each of the work stages?
Correct Answer:

Verified
a.Stage B. Capacity is 20 unit...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: A manufacturing firm that produces a standardized
Q10: Explain the relationship between custom, option, and
Q23: Appliances and iPods are examples of _
Q24: A(n) _ is a group of _
Q27: Marketing Product Characteristics/Decisions for the Product-Process Matrix
Q43: An order fulfillment process normally operates two
Q43: What type of process would a paper
Q66: As one moves up the hierarchy of
Q78: Transferring material between two non-adjacent workstations, waiting
Q92: Explain each axis of the product-process matrix.