The following five jobs, along with their processing time and due dates, are given below. The following five jobs, along with their processing time and due dates, are given below.    a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.
a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs
b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.

Correct Answer:

verifed

Verified

a.Sequence the jobs as C-B-E-D-A. Flow t...