A Company Has Used PERT for a Project and Wants

Question 15

Essay

A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks: A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:    a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?