Multiple Choice
Which of the following is used to develop detailed machine- and labor-use schedules that consider available capacity?
A) capacity requirements planning (CRP)
B) capable to promise planning (CTP)
C) computer-aided process planning (CAPP)
D) computer-aided manufacturing (CAM)
Correct Answer:

Verified
Correct Answer:
Verified
Q24: Which of the following has included management
Q31: MRP is a process that uses bills
Q33: The _ process uses the information from
Q48: The process of _ involves determining the
Q54: The inventory production schedule is a statement
Q67: Materials requirements planning (mrp) normally would use
Q69: _ tags can be attached to inventory
Q70: Purchase orders convey authority for the manufacture
Q84: Variance analysis is the process of comparing
Q108: Supply chain management software provides _ to