Graham Pottery Inc -The Total Manufacturing Cycle Time Is:
A) 76 Hours
B)

Question 63

Multiple Choice

Graham Pottery Inc.
Graham Pottery Inc. produces an item that gives rise to the following activities:
 Activity  Hours  Processing (two departments)  25 Inspecting 2 Rework 1 Moving (three moves)  6 Waiting (for the second process)  18 Storage (before delivery to the customer)  24\begin{array} { l c } \text { Activity } & \text { Hours } \\\hline \text { Processing (two departments) } & 25 \\\text { Inspecting } & 2 \\\text { Rework } & 1 \\\text { Moving (three moves) } & 6 \\\text { Waiting (for the second process) } & 18 \\\text { Storage (before delivery to the customer) } & 24\end{array}

-The total manufacturing cycle time is:


A) 76 hours
B) 52 hours
C) 28 hours
D) 34 hours

Correct Answer: