A Project Has Been Assigned a Discount Rate of 12

Question 57

Multiple Choice

A project has been assigned a discount rate of 12 percent.If the project starts immediately,it will have an initial cost of $480 and cash inflows of $350 a year for three years.If the start is delayed one year,the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years.What is the value of the option to wait?


A) $.70
B) $1.08
C) $1.67
D) $2.20
E) $.20