Multiple Choice
A project has an initial cost of $26,000,a discount rate of 11.7 percent,a life of 5 years,and an NPV of $11,216.Given this,you know that the project is expected to earn a return:
A) equal to 11.7 percent of $26,000 plus an additional $11,216.
B) of $11,216 in total.
C) equal to 11.7 percent of $37,216 (= $26,000 + 11,216) .
D) of 11.7 percent of $11,216.
E) of $26,000 minus $11,216.
Correct Answer:

Verified
Correct Answer:
Verified
Q44: Which method(s)of project analysis is(are)best suited for
Q45: Leslie is charged with determining which small
Q46: Project A is opening a bakery at
Q47: Flo's Flowers has a proposed project with
Q48: Project A costs $84,500 and has cash
Q50: An investment with an initial cost of
Q51: How should a profitability index of zero
Q52: Using the internal rate of return method,a
Q53: The internal rate of return tends to
Q54: You are considering two independent projects that