Multiple Choice
Worthington Inc.is considering a project that has the following cash flow data.What is the project's payback?
Year
0
1
2
3
Cash flows
−$500
$150
$200
$300
A) 2.03 years
B) 2.25 years
C) 2.50 years
D) 2.75 years
E) 3.03 years
Correct Answer:

Verified
Correct Answer:
Verified