Multiple Choice
A network of arrows and nodes representing project activities that require an expenditure of time and resources and the completion of initiation of activities,respectively,is called
A) a Gantt chart.
B) a PERT diagram.
C) a SDLC cycle.
D) CASE.
Correct Answer:

Verified