Multiple Choice
During implementation,testing of the software and training of the users can be carried out in parallel until the final acceptance testing which the users have to do after they are trained.It is predicted to take 10 days to do program testing,5 to test the system modules and 5 for acceptance testing.It is expected to take 22 days to train users.How long is the critical path?
A) 22 days
B) 20 days
C) 25 days
D) 27 days
Correct Answer:

Verified
Correct Answer:
Verified
Q17: In many cases,the accountant or internal auditor
Q18: Briefly describe different types of feasibility analysis
Q19: When considering new opportunities for technology within
Q20: Consider the following diagram.<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB3106/.jpg" alt="Consider the
Q21: The ability to manage different groups of
Q23: Which of the following cannot be used
Q24: From least risky to most risky,which of
Q25: Making requirement analysis of a new system:<br>A)is
Q26: Which is the highest level of system
Q27: A document that outlines the specifications for