Multiple Choice
Which of the following regarding project times is not true?
A) The latest start time is the latest possible time at which a task can commence without delaying the project.
B) The latest start time is used in calculating the amount of slack or spare time available for disruptions.
C) Activities on the critical path can have slack time built into them.
D) The difference between the earliest finish time and the latest finish time is the amount of slack that is available.
Correct Answer:

Verified
Correct Answer:
Verified
Q40: Building in internal controls after the systems
Q41: There are two types of slack:<br>A)favourable and
Q42: Which of the following statement is not
Q43: Which of the following statements regarding in-house-developed
Q44: The two levels of accounting software are:<br>A)Mid-range
Q46: Which of the following is unlikely a
Q47: Which of the following is not an
Q48: What are the steps in preparing a
Q49: Which of the following descriptions regarding critical
Q50: The systems development project requires a mix