Multiple Choice
If any activity that is on the critical path is delayed:
A) The finishing day of the project will not be affected.
B) The finishing day of the project will be brought forward.
C) The finishing day of the project will be delayed.
D) One should no longer follow the critical path for calculating project completion time.
Correct Answer:

Verified
Correct Answer:
Verified