Multiple Choice
The total fixed overhead variance is calculated by the following formula:
A) Total actual overhead - Total applied overhead.
B) AFOH -Standard overhead rate *SH.
C) AFOH - SFOR * SH.
D) AFOH - SFOR F* AH.
E) Total actual overhead - SFOR * SH.
Correct Answer: