Vaughn, Inc The Following Are Two of the Jobs Completed During the Drivers
Question 132
Question 132
Multiple Choice
Vaughn, Inc., has identified the following overhead costs and activity drivers for next year: Overhead Item Setup costs Ordering costs Maintenance Power Expected Cost$200,00080,000400,00040,000Activity Driver Number of setups Number of orders Machine hours Kilowatt hours Expected Quantity2501,6002,00040,000 The following are two of the jobs completed during the year: Direct materials Direct labour Units completed Direct labour hours Number of setups Number of orders Machine hours Kilnwratt houre Job 10A$3,000$2,80010050142030 Jab20 E$4,000$4,800160804525$5 The company's normal activity is 2,000 direct labour hours. -Refer to the figure.If the four activity drivers are used to allocate overhead costs,what would be the total overhead allocated to Job 10A?
A) $4,830 B) $5,030 C) $5,533 D) $5,630
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge