Essay
Duff Company uses a job-order costing system to compute product costs.There are two producing departments (P1 and P2)and two support departments (S1 and S2).The costs incurred in S1 and S2 are allocated to Departments A and B and included in their factory overhead rates for costing products.S1 costs are allocated based on the number of employees,S2 costs are allocated based on direct labour hours,and the production departmental overhead rates are also based on direct labour hours.The following data are available for a recent period:
a.Prepare a schedule allocating the support department costs to the producing departments using the sequential allocation method.The department with the greatest percentage of interdepartmental services should be allocated first.
b.Determine the overhead rates per direct labour hour for P1 and P2.
c.Job A2 was completed during the period at a cost of $26,000 for direct materials and direct labour costs.This job required 21 direct labour hours in Department P1 and 15 direct labour hours in Department P2.What was the total cost of Job A2?
Correct Answer:

Verified
Correct Answer:
Verified
Q45: Consider the following statement: Each product is
Q46: Lake Corporation manufactures two products,AA and BB,from
Q47: What is one of the potential advantages
Q48: Oaks Company has two support departments,
Q49: Which of the following methods allocates support
Q51: Dean Manufacturing Company has two support
Q52: Which of the following allocation methods assumes
Q53: Xi Print operates a copy business
Q55: Why are joint costs allocated?<br>A)because of GAAP
Q126: Which of the following methods allocates a