Multiple Choice
A time-and-motion study revealed that it should take 2 hours to produce a product that currently takes 6 hours to produce.Labour is $8 per hour.What are the value-added costs?
A) $8
B) $16
C) $32
D) $48
Correct Answer:

Verified
Correct Answer: