Multiple Choice
Setup time for a product is 12 hours.A firm that uses JIT and produces the same product has reduced setup time by 1 hour.Setup labour is $20 per hour.What would be the currently attainable standard for setup time if the company wants to reduce non-value-added costs by 40 percent next year?
A) 7.6 hours
B) 7.2 hours
C) 6.6 hours
D) 4.8 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q26: What incentive specifically relates to sharing the
Q27: Froelech Company has developed capacity standards.
Q28: What process dimension of the activity-based management
Q29: Gibson,Inc.,has developed ideal standards for four
Q30: What is the term for the effort
Q32: What technique improves performance of activities and
Q33: A company has 20 days of finished
Q34: What is multiplied by standard quantity to
Q35: What is an activity output measure?<br>A)the activities
Q36: Which of the following is a value-added