Multiple Choice
What does a withdrawal Kanban specify?
A) how much should be produced to replace inventory
B) the quantity that a subsequent process should withdraw from the preceding process
C) when customers should be notified to pick up orders
D) when suppliers should be notified to deliver more parts
Correct Answer:

Verified
Correct Answer:
Verified