Multiple Choice
What is the NPV for a project whose cost of capital is 15 percent and initial after-tax cost is $5,000,000 and is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4?
A) $1,700,000
B) $371,764
C) -$137,053
D) -$4,862,947
Correct Answer:

Verified
Correct Answer:
Verified