Multiple Choice
Ontel engineers proposed developing a 10-Gigahertz microprocessor in early 2011 at a cost of $20 million for a working prototype.By mid-2012,the $20 million had been spent with no prototype.The engineers request an additional $10 million to finish the project.For convenience,assume the marginal cost of producing the chip once it is developed is zero.
-In deciding whether to continue the 10-Gigahertz chip,Ontel executives should compare the __________ to the expected revenues.
A) $20 million spent plus the extra $10 million
B) $20 million spent
C) extra $10 million
D) $20 million spent minus the extra $10 million
E) $20 million spent plus the extra $10 million plus $5 million for cost overruns
Correct Answer:

Verified
Correct Answer:
Verified
Q163: Opportunity cost is best defined as<br>A) marginal
Q164: Ontel engineers proposed developing a 10-Gigahertz microprocessor
Q165: The opportunity cost of an activity is
Q166: Joe has decided to purchase his textbooks
Q167: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB3713/.jpg" alt=" -The least important
Q169: If two variables move together but are
Q170: If one fails to account for opportunity
Q171: "Economic development reduces environmental quality and should
Q172: We do not expect economists to agree
Q173: Jackson just took out a $1,000 loan