Multiple Choice
Which of the following is a drawback of the waterfall method?
A) It is unable to adapt to changes of the business landscape.
B) Its activities occur at the same time which makes it hard to monitor them.
C) It estimates deliveries based on the time and requirements available.
D) Its SDLC tasks occur in non-sequential manner.
Correct Answer:

Verified
Correct Answer: