menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Systems in Organizations
  4. Exam
    Exam 12: Project Management and Strategic Planning
  5. Question
    A(n) ________ in a Work Breakdown Structure Refers to a Task
Solved

A(n) ________ in a Work Breakdown Structure Refers to a Task

Question 37

Question 37

Multiple Choice

A(n) ________ in a work breakdown structure refers to a task that needs to be completed before a particular task can begin.


A) subtask
B) successor
C) concurrent
D) predecessor

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q10: Scope creep refers to a strategy in

Q12: What is change management?

Q35: A kick-off meeting involves _.<br>A) project stakeholders

Q35: Change management refers to a structured approach

Q40: In which of the following areas of

Q41: A project charter ensures that there is

Q42: The human tendency to choose information to

Q49: Which of the following is most likely

Q77: A(n)_ bias refers to a belief that

Q99: What are the essential characteristics that a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines