Multiple Choice
Which of the following best defines a critical path in a project?
A) the shortest path through a project undertaken to achieve a fixed deadline
B) the longest project path that identifies tasks that cannot be delayed without affecting the finish date
C) the path that takes into account all possible factors that can delay a project to estimate a deadline
D) the shortest path undertaken in a monitoring process in which there is no fixed deadline
Correct Answer:

Verified