Multiple Choice
Why is it usually necessary to use the time value of money when performing a cost benefit analysis?
A) For an investment project to be considered,costs must have a higher dollar value from benefits.
B) In most investment projects costs are incurred up front,but benefits are provided in the future.
C) For practical purposes,a dollar today may be considered to be equal to a dollar at some future time.
D) Although costs and benefits generally occur concurrently,the benefits will accrue value over time,due to interest.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: How can we make a financial decision
Q10: If the risk-free rate of interest (r<sub>f</sub>)is
Q51: Use the information for the question(s) below.<br>
Q74: Whenever a good trades in a competitive
Q74: A dollar today and a dollar in
Q75: Stella deposits $5,000 in a savings account
Q78: Why should you approach every problem by
Q80: Which of the following statements is INCORRECT?<br>A)In
Q82: An investment will pay $205,000 at the
Q84: To enable costs and benefits to be