Multiple Choice
What is the last step in developing an activity-based costing system?
A) Estimate the total quantity of the cost driver.
B) Estimate the total indirect costs of each activity.
C) Identify the activities.
D) Allocate costs to the cost object.
Correct Answer:

Verified