Multiple Choice
The Northwest Savings Bank is implementing a new computer system.It requires that the final testing systems approach is both safe and cost-effective.The bank has planned to implement the new system over the course of the next 18 months.The bank should choose
A) parallel operation.
B) the direct approach.
C) modular conversion.
D) the cutoff approach.
Correct Answer:

Verified
Correct Answer:
Verified