Multiple Choice
The following account balances at the beginning of January were selected from the general ledger of Ocean City Manufacturing Company:
Additional data:
1.Actual manufacturing overhead for January amounted to $62,000.
2.Total direct labor cost for January was $63,000.
3.The predetermined manufacturing overhead rate is based on direct labor cost.The budget for the year called for $250,000 of direct labor cost and $350,000 of manufacturing overhead costs.
4.The only job unfinished on January 31 was Job No.151,for which total direct labor charges were $5,200 (800 direct labor hours) and total direct material charges were $14,000.
5.Cost of direct materials placed in production during January totaled $123,000.There were no indirect material requisitions during January.
6.January 31 balance in raw materials inventory was $35,000.
7.Finished goods inventory balance on January 31 was $34,500.
What is the work in process inventory balance on January 31?
A) $7,280
B) $22,914
C) $26,480
D) $50,914
Correct Answer:

Verified
Correct Answer:
Verified
Q88: If a job consists of a batch
Q109: Manufacturing overhead has an underallocated balance of
Q142: Peterson Company gathered the following information for
Q143: To record depreciation on factory equipment,the needed
Q145: Beta Company uses a predetermined overhead rate
Q148: Records for Speedy's Custom Networks contained the
Q149: Solid Oak Bureau Company uses job costing.Solid
Q152: Missy & Daughters allocates manufacturing overhead to
Q198: Overallocated manufacturing overhead costs occur when the
Q328: Manufacturing overhead is underallocated if the amount<br>A)estimated