If the Purchasing Manager Purchased a Greater Quantity of Raw

Question 167

Multiple Choice

If the purchasing manager purchased a greater quantity of raw materials than budgeted, but paid the Standard Price (SP) , which variance may be affected?


A) Materials price variance
B) Materials quantity variance
C) Both of the variances may be affected
D) Neither of the variances may be affected