Multiple Choice
Schenley Manufacturing builds playground equipment that it sells to elementary schools and municipalities.Schenley's management has contracted you to perform a variance analysis on the fixed manufacturing overhead for its line of slides.Schenley's cost accounting team informs you that it allocates fixed overhead based on machine hours.This period production was budgeted at 375 slides.Budgeted and actual production data follows:
What is the fixed manufacturing overhead volume variance in this period?
A) $2,750 unfavorable
B) $1,320 unfavorable
C) $2,750 favorable
D) $1,320 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q20: A favorable direct materials price variance and
Q98: A favorable direct labor efficiency variance and
Q125: How is the direct labor efficiency variance
Q198: The actual cost of direct materials is
Q199: Madden Corporation manufactures t-shirts,which is its only
Q200: Hushovd Iron Works has collected the following
Q201: Jennings Manufacturing gathered the following flexible budget
Q204: The _ "shows how well management has
Q205: Active Lifestyle Beverages gathered the following information
Q211: A price variance for production inputs is