Multiple Choice
A project costs $91,000 today and is expected to generate cash flows of $11,000 per year for the next 20 years.The firm has a cost of capital of 8 percent.Should this project be accepted,and why?
A) Yes, the project should be accepted since it has a NPV = $15,391.23.
B) Yes, the project should be accepted since it has a NPV = $13,610.89.
C) Yes, the project should be accepted since it has a NPV = $16,999.62.
D) None of these answers is correct.
Correct Answer:

Verified
Correct Answer:
Verified