Multiple Choice
What is the factor in Net Present Value analysis that normally involves the least degree of uncertainty?
A) the future cash flows.
B) the cost of the initial investment.
C) the life of the project.
D) the discount rate.
Correct Answer:

Verified
Correct Answer:
Verified