Solved

What Variance Does the Difference Between the Actual Cost of the Direct

Question 74

Multiple Choice

What variance does the difference between the actual cost of the direct labour hours worked and the planned cost of the direct labour hours measure?


A) The direct labour efficiency variance.
B) The direct labour rate variance.
C) The total direct labour variance.
D) None of the above.